The Silver Dart Project Planner

Hi guys...

This page is intended to keep everyone up-to-date with progress on the SD project. I will list all the tasks, resources, timings etc in order to keep timelines short, forsee delays and organise volunteers time etc.

Let me know if there is anything missing off this list. I will update it daily so keep an eye on it.

Cheers... Goose


Last updated: 12:22pm Wednesday January 21, 2009.

Update: We are all but finished and the radio setup is complete.
This week is being spent doing final electronics setup and hopefully ground testing this weekend.

See updated pictures on the Stetson website. Cheers, Goose.

New schedule as of December 4, 2008.

Task Items Due Status
Build the rear fuselage Cut & assemble bottom frame 14 Dec Complete
Cut & assemble vertical members 14 Dec Complete
Cut & assemble top frame 14 Dec Complete
Bind joints with kelvar 14 Dec Complete
Paint the rear fuselage to simulate bamboo 14 Dec Complete
Rudder Construction Build the rudder frame 14 Dec Complete
Cover and paint rudder assembly 14 Dec Complete
Paint rudder CF bamboo 14 Dec Complete
Rig the rudder bracing wires 14 Dec Complete
Construct rudder pins and attach to the rear fuselage 14 Dec Complete
Build the wings Attach wings to jig 14 Dec Complete
Construct struts, pins and stain 14 Dec Complete
Install struts & bracing brackets 14 Dec Complete
Install bracing wires 14 Dec Complete
Install wingtip CF 14 Dec Complete
Repaint aileron frames to bamboo 15 Dec Complete
Install aileron fittings & conn. rod 16 Dec Complete
Install ailerons 16 Dec Complete
Install aileron control wires 17 Dec Complete
Build the fuselage center section Cut and shape side frames 4 Dec Complete
Glue side frames & reinforcement 4 Dec Complete
Cut and glue interconnecting members + reinf. 7 Dec Complete
Construct & attach wing attachment brackets 14 Dec Complete
Mock-up wheels based on manufacturers info 21 Jan Complete
Construct & attach rear landing gear 22 Jan Complete
Construct & attach motor mounting tray 21 Dec Complete
Construct & attach motor thrust adjustment assembly 21 Dec Complete
Construct & install servo tray 21 Dec Complete
Construct & install pilots seat and steering wheel 21 Dec Complete
Final assembly Construct & install rudder control cables - Complete
Construct & install steerable nosewheel components - Complete
Construct & install elevator control cables - Complete
Install all radio gear - Complete
Install wheels - On hold
Install pilot - Complete
Install all scale items - Complete
Flight preparation Establish and set C of G - -
Lateral balance - -
Establish control movement and program radio Jan 31- Complete
Ground test Test and tweak ground handling & operation - -
Flight Maiden flight - -
Post flight inspection Ensure integrity and repair where needed - -


Completed to date.

Task Due Status
Michel and Goose are building the aileron frames 7 Nov Complete
Marc is painting the wings & rudder this weekend 8 Nov, Goose to deliver Complete
Stabilizer components to be painted 13 Nov Complete
Paint the aileron frames 13 Nov Complete
Michel is continuing the assembly of the stabilizer 14 Nov Complete
Goose continues with the forward fuselage construction 16 Nov Complete
The wings (one at a time) will be attached to the fuselage jig 17 Nov Complete
The wing struts will be cut, shaped and drilled for 440 connection rods 19 Nov Complete
Rigging brackets will be made 20 Nov 400% Complete
Attach the stabilizer to the fuselage 20 Nov Complete
Paint the forward fuselage to simulate bamboo 21 Nov Complete


<